GSU transformer average lead time (Wood Mackenzie survey)

GSU transformer average lead time (Wood Mackenzie survey), weeks, Q2 2025 to Q2 2025. Every value is listed in the table below.
GSU transformer average lead time (Wood Mackenzie survey), weeks, Q2 2025 to Q2 2025. Every value is listed in the table below.
PeriodGSU transformer average lead time (Wood Mackenzie survey) (weeks)
Q2 2025143
PeriodValueSource
Q2 2025SourcedWood Mackenzie (Mind the gap, opinion) · 2025-10-15Open the source → weeksWood Mackenzie (Mind the gap, opinion) ↗ secondary reportGSUs saw a slight decline quarter over quarter in Q2, easing to 143 weeks on average