Skip to content
Substrata
Join

Lead time · US · weeks

GSU transformer average lead time (Wood Mackenzie survey)

GSU transformer average lead time (Wood Mackenzie survey), weeks, Q2 2025 to Q2 2025. Every value is listed in the table below.
PeriodValueSource
Q2 2025SourcedWood Mackenzie (Mind the gap, opinion) · 2025-10-15Open the source → weeksWood Mackenzie (Mind the gap, opinion) ↗ secondary reportGSUs saw a slight decline quarter over quarter in Q2, easing to 143 weeks on average

Read from the sources Read from the source by an agent; quote matched mechanically against the fetched page; not yet reviewed by a person, 2026-09-24. Each value links the page it came from and quotes the sentence that carries it.