Lead time · US · weeks

Large (substation power + GSU) transformer lead time range

Large (substation power + GSU) transformer lead time range, weeks, 2024 to 2024. Every value is listed in the table below.
PeriodValueSource
2024SourcedPresident's National Infrastructure Advisory Council (NIAC), citing Wood Mackenzie · 2024-06Open the source → weeksPresident's National Infrastructure Advisory Council (NIAC), citing Wood Mackenzie ↗ primaryLarge transformers, both substation power and generator step-up transformers, have lead times ranging from 80 to 210 weeks.Range 80-210 weeks; value = upper bound.