Grain-oriented electrical steel (GOES)

The specially grown steel inside a large power transformer. Few mills can make it, and a new mill takes years.

Searching is free and needs no AI. Summaries use your own AI model.

Severity
How this is computedSum of four judged scores, each 0–3: concentration + substitution + lead time + inelasticity.Method →Code →
How hard it binds, 0 to 12
When it bites
Now
judged 2026-09-15
Evidence
Verified
7 maker rows

01Key numbers

dated, each linked to its source

What the text on this page claims, and the number behind it

  • Few mills can make it, and a new mill takes years. Measured

    One US producer, per DOE; a new line announced in India reaches full capacity only by 2030.

    Number of US domestic GOES producers: SourcedUS DOE final rule, distribution transformer standards (Federal Register 2024-07480)Open the source → count, 2024JSW JFE Electrical Steel (India) GOES capacity: SourcedJFE Steel (press release)Open the source → tonnes/year, 2030

  • Capacity · USNumber of US domestic GOES producersSourcedUS DOE final rule, distribution transformer standards (Federal Register 2024-07480) · 2024Open the source → count2024
    PeriodValueSource
    2024SourcedUS DOE final rule, distribution transformer standards (Federal Register 2024-07480) · 2024-04-22Open the source → countUS DOE final rule, distribution transformer standards (Federal Register 2024-07480) ↗ primaryDOE notes there is one domestic producer of amorphous steel and one domestic producer of GOES.Cleveland-Cliffs Butler Works (PA).

    Read from the sources Read from the source by an agent; quote matched mechanically against the fetched page; not yet reviewed by a person, 2026-09-24. Each value links the page it came from and quotes the sentence that carries it.

  • Capacity · company: JSW JFE Electrical Steel (India)JSW JFE Electrical Steel (India) GOES capacitySourcedJFE Steel (press release) · 2030Open the source → tonnes/year2030 · target or forecastHow this is computedThe latest value in a series minus the value before it, divided by the earlier value, same series and unit.50,000 (Aug 2025) → 350,000 (2030).Method →Code → vs Aug 2025
    JSW JFE Electrical Steel (India) GOES capacity, tonnes/year, Aug 2025 to 2030. Every value is listed in the table below.
    PeriodValueSource
    2030SourcedJFE Steel (press release) · 2025-08-04Open the source → tonnes/year target or forecastJFE Steel (press release) ↗ primaryIn this expansion plan, we will double the manufacturing capacity of the J2ES Vijayanagar site from the initial plan, to 100,000 tonnes per year and increase the current manufacturing capacity of the J2ES Nashik site fivefold, from 50,000 tonnes per year to 250,000 tonnes per year. The manufacturing capacity of the J2ES Vijayanagar site and the J2ES Nashik site will be significantly increased to a total of 350,000 tonnes per year.Planned: Vijayanagar 100,000 t/y by 2027, Nashik 250,000 t/y phased 2028-2030.
    Aug 2025SourcedJFE Steel (press release) · 2025-08-04Open the source → tonnes/yearJFE Steel (press release) ↗ primaryIn this expansion plan, we will double the manufacturing capacity of the J2ES Vijayanagar site from the initial plan, to 100,000 tonnes per year and increase the current manufacturing capacity of the J2ES Nashik site fivefold, from 50,000 tonnes per year to 250,000 tonnes per year. The manufacturing capacity of the J2ES Vijayanagar site and the J2ES Nashik site will be significantly increased to a total of 350,000 tonnes per year.Current Nashik capacity 50,000 t/y.

    Read from the sources Read from the source by an agent; quote matched mechanically against the fetched page; not yet reviewed by a person, 2026-09-24. Each value links the page it came from and quotes the sentence that carries it.

  • Other · USUS electrical steel demand for distribution transformersSourcedUS DOE final rule, distribution transformer standards (Federal Register 2024-07480) · 2024Open the source → tonnes/year2024
    PeriodValueSource
    2024SourcedUS DOE final rule, distribution transformer standards (Federal Register 2024-07480) · 2024-04-22Open the source → tonnes/yearUS DOE final rule, distribution transformer standards (Federal Register 2024-07480) ↗ primaryThe current domestic demand for electrical steel used in distribution transformers is estimated to be approximately 225,000 metric tons, which is approximately equal to the global capacity for amorphous material.All core steel (GOES + amorphous), DOE estimate.

    Read from the sources Read from the source by an agent; quote matched mechanically against the fetched page; not yet reviewed by a person, 2026-09-24. Each value links the page it came from and quotes the sentence that carries it.

  • Other · USUS GOES consumption for distribution transformersSourcedUS DOE final rule, distribution transformer standards (Federal Register 2024-07480), citing MTC comment · 2023Open the source → tonnes/year2023
    PeriodValueSource
    2023SourcedUS DOE final rule, distribution transformer standards (Federal Register 2024-07480), citing MTC comment · 2024-04-22Open the source → tonnes/yearUS DOE final rule, distribution transformer standards (Federal Register 2024-07480), citing MTC comment ↗ primaryMTC provided US import and consumption data for GOES and commented that U.S. consumption of GOES for distribution transformers is approximately 175K MT.Stakeholder (MTC) estimate recorded in DOE rule; "175K MT".

    Read from the sources Read from the source by an agent; quote matched mechanically against the fetched page; not yet reviewed by a person, 2026-09-24. Each value links the page it came from and quotes the sentence that carries it.

  • Other · USGOES share of total LPT manufacturing costSourcedUS DOE (Electric Grid Supply Chain Review: LPTs and HVDC, citing Commerce 2020 survey) · 2020Open the source → %2020
    PeriodValueSource
    2020SourcedUS DOE (Electric Grid Supply Chain Review: LPTs and HVDC, citing Commerce 2020 survey) · 2022-02Open the source → %US DOE (Electric Grid Supply Chain Review: LPTs and HVDC, citing Commerce 2020 survey) ↗ primaryAccording to a 2020 U.S. Department of Commerce survey of 87 domestic manufacturers of LPT components, GOES accounts for about 25 percent of the total manufacturing costs for transformers, while labor accounts for 36 percent of costs on average

    Read from the sources Read from the source by an agent; quote matched mechanically against the fetched page; not yet reviewed by a person, 2026-09-24. Each value links the page it came from and quotes the sentence that carries it.

  • Other · USShare of US GOES laminations importedSourcedUS DOE (Electric Grid Supply Chain Review: LPTs and HVDC, citing Commerce 2020) · 2019Open the source → %2019
    PeriodValueSource
    2019SourcedUS DOE (Electric Grid Supply Chain Review: LPTs and HVDC, citing Commerce 2020) · 2022-02Open the source → %US DOE (Electric Grid Supply Chain Review: LPTs and HVDC, citing Commerce 2020) ↗ primaryThe imports of GOES laminations are approximately 88% with 95% of the imports coming from Canada and Mexico for both wound cores and stacked coresFor wound and stacked cores; 95% of imports from Canada and Mexico.

    Read from the sources Read from the source by an agent; quote matched mechanically against the fetched page; not yet reviewed by a person, 2026-09-24. Each value links the page it came from and quotes the sentence that carries it.

Every series on every bottleneck — filter, compare and download.

02Why it holds things up

The binding constraint on datacentre energisation. Large power transformers queue for years, and the core steel behind them is made on a small number of qualified lines.

Grade that ships · M3-class grain-oriented silicon steel, coil, coated.

Part of the process · Energy, which takes years to loosen once somebody decides to.

03Severity

judged 2026-09-15 · a judgement, not a measurement

How this is computedSum of four judged scores, each 0–3: concentration + substitution + lead time + inelasticity.Method →Code → / 12

How few suppliers qualify
Estimate, not a measurementEvery large transformer needs it, few mills make it, and a mill takes years. The transformer queue is partly a GOES queue.By Substrata, open to challenge · 2026-09-15 / 3
How hard to replace
Estimate, not a measurementEvery large transformer needs it, few mills make it, and a mill takes years. The transformer queue is partly a GOES queue.By Substrata, open to challenge · 2026-09-15 / 3
Decision to new capacity
Estimate, not a measurementEvery large transformer needs it, few mills make it, and a mill takes years. The transformer queue is partly a GOES queue.By Substrata, open to challenge · 2026-09-15 / 3
Can the buyer walk away
Estimate, not a measurementEvery large transformer needs it, few mills make it, and a mill takes years. The transformer queue is partly a GOES queue.By Substrata, open to challenge · 2026-09-15 / 3

Every large transformer needs it, few mills make it, and a mill takes years. The transformer queue is partly a GOES queue.

04Who makes it

7 verified of 7 rows

05What it rests on, and what rests on it

each row quotes the page it rests on

Depended on by

A recorded dependency is a sentence, not a share, a volume or a contract. Walk it on a portfolio →

06Rules that govern it

All policy →

07What would remove it

  • Amorphous metal transformer coresEstimate, not a measurementIn production at scale, but only for part of the problem. ABB has sold amorphous metal distribution transformers for two decades; the constraint is applicability rather than maturity, because the lower saturation induction means a larger core cross-section, larger coils and a larger footprint — acceptable on a pole, not on a grid-scale unit.By Substrata, open to challenge · 2026-09-18Supporting source → · In production at scale

    Every distribution transformer built on amorphous ribbon is one that does not consume GOES — ABB reports about 70 percent lower no-load losses as well. It does not touch the large power transformers in the way: amorphous has lower saturation, so the core must be physically bigger, which is where the substitution stops.

All science →

08Science pipeline

34 papers, preprints and grants collected, unreviewed
  1. Research32 (Computed: Items per stage = papers, preprints and grants collected for the bottleneck whose relevance score is 2 or more, placed on a stage by the rule in lib/science.ts; judgements are counted separately.)+2 (Computed: Items first collected in the last 7 days whose publication or award date is within the last 30 days.) new
  2. Lab2 (Computed: Items per stage = papers, preprints and grants collected for the bottleneck whose relevance score is 2 or more, placed on a stage by the rule in lib/science.ts; judgements are counted separately.)
  3. Pilot0 (Computed: Items per stage = papers, preprints and grants collected for the bottleneck whose relevance score is 2 or more, placed on a stage by the rule in lib/science.ts; judgements are counted separately.)
  4. Early0 (Computed: Items per stage = papers, preprints and grants collected for the bottleneck whose relevance score is 2 or more, placed on a stage by the rule in lib/science.ts; judgements are counted separately.)
  5. Scale0 (Computed: Items per stage = papers, preprints and grants collected for the bottleneck whose relevance score is 2 or more, placed on a stage by the rule in lib/science.ts; judgements are counted separately.)

judged, with a citation claimed, no citationNumber: papers, preprints and grants the feeds collected — unreviewed

The full pipeline, by stage →

09What we have predicted

  • 2026-09-15open until 2028-01-31

    Large power transformer lead times will still be three years or longer at the end of 2027, despite the capacity expansions announced through 2026.

    Settled by · Quoted lead times for a 100 MVA-class unit from at least two major manufacturers or a published industry survey, dated in the last quarter of 2027.

All calls →

10Who could fund relief

Is funding the constraint? · Money is part of it

A new mill is buildable and expensive, and the reason few are built is that demand is thought temporary. That is a capital judgement, so capital could change it — slowly.

  • European Investment BankDevelopment bank

    The EU’s own bank, lending long-term for infrastructure, energy networks and industrial capacity that meets EU policy objectives.

    Development bank will not fund · Anything outside its mandate, however commercially sound. It is patient and cheap and narrow, in that order.

  • KfWDevelopment bank

    Germany’s promotional bank, funding industrial transformation and energy infrastructure on behalf of the federal government.

A mandate covering the kind of asset that would relieve this row. Not a claim that anyone has funded one, and not advice.

11What has happened

2 dated
  1. 2026-09-14
    NeutralCapacityCN

    ArcelorMittal and China Oriental open a 1.8 Mt/yr electrical steel joint venture in Changzhou; the first phase is non-oriented.

    gmk.center ↗secondary source

    The sentence that says so

    “The total production capacity of the facility in Changzhou will be 1.8 million tonnes of high-quality electrical steel sheets.”

  2. 2026-03-27
    TightensPolicyEU

    The European Commission opens a safeguard investigation into imports of grain-oriented electrical steel.

    aslgate.com ↗official source

    The sentence that says so

    “on March 27, 2026, the European Commission issued a notice initiating a safeguard investigation on certain Grain-Oriented Electrical Steel (GOES) products.”

All events →

12What this holds up

2 loops
  • Energyone turn: Months to years

    Worst judgement on this loop: How this is computedThe highest severity score among the bottlenecks recorded as gates on the loop.Method →Code →, judged 2026-09-15

  • Worst judgement on this loop: How this is computedThe highest severity score among the bottlenecks recorded as gates on the loop.Method →Code →, judged 2026-09-15

A loop is one design, build and measure turn. Severity is a dated judgement on a 0–12 scale, not a measurement, and the judgements are not added together — the figure shown is the worst single one.