Backlog · company: GE Vernova · GW

Gas turbine slot reservation agreements (not in backlog)

How this is computedThe latest value in a series minus the value before it, divided by the earlier value, same series and unit.56 (31 Mar 2026) → 63 (30 Jun 2026).Method →Code → vs 31 Mar 2026 · tightens
Gas turbine slot reservation agreements (not in backlog), GW, 31 Mar 2025 to 30 Jun 2026. Every value is listed in the table below.
PeriodValueSource
30 Jun 2026SourcedGE Vernova (Q2 2026 earnings release, SEC 8-K Ex.99) · 2026-07-22Open the source → GWGE Vernova (Q2 2026 earnings release, SEC 8-K Ex.99) ↗ primaryConverted 10 GW of existing slot reservation agreements to orders and shipped 3 GW of equipment; resulting in backlog growth from 44 to 53 GW and an increase in slot reservation agreements from 56 to 63 GW.
31 Mar 2026SourcedGE Vernova (Q1 2026 earnings release, SEC 8-K Ex.99) · 2026-04-22Open the source → GWGE Vernova (Q1 2026 earnings release, SEC 8-K Ex.99) ↗ primaryConverted 6 GW of existing slot reservation agreements to orders and shipped 4 GW of equipment; resulting in backlog growth from 40 to 44 GW and an increase in slot reservation agreements from 43 to 56 GW.
31 Dec 2025SourcedGE Vernova (Q4 2025 earnings release, SEC 8-K Ex.99) · 2026-01-28Open the source → GWGE Vernova (Q4 2025 earnings release, SEC 8-K Ex.99) ↗ primaryConverted 8 GW of existing slot reservation agreements to orders and shipped 3 GW of equipment; resulting in backlog growth from 33 to 40 GW and an increase in slot reservation agreements from 29 to 43 GW.
30 Sep 2025SourcedGE Vernova (Q3 2025 earnings release, SEC 8-K Ex.99) · 2025-10-22Open the source → GWGE Vernova (Q3 2025 earnings release, SEC 8-K Ex.99) ↗ primaryConverted 7 GW of existing slot reservation agreements to orders and shipped 4 GW of equipment; resulting in backlog growth from 29 to 33 GW and an increase in slot reservation agreements from 25 to 29 GW
30 Jun 2025SourcedGE Vernova (Q2 2025 earnings release, SEC 8-K Ex.99) · 2025-07-23Open the source → GWGE Vernova (Q2 2025 earnings release, SEC 8-K Ex.99) ↗ primaryConverted 3 GW of existing slot reservation agreements to orders and shipped 5 GW of equipment; resulting in backlog remaining at 29 GW, while growing slot reservation agreements from 21 GW to 25 GW.
31 Mar 2025SourcedGE Vernova (Q1 2025 earnings release, SEC 8-K Ex.99) · 2025-04-23Open the source → GWGE Vernova (Q1 2025 earnings release, SEC 8-K Ex.99) ↗ primarySigned 7 gigawatts of gas turbine orders, raising our Gas Power equipment backlog to 29 gigawatts; secured another 7 gigawatts of gas turbine slot reservation agreements, with 21 gigawatts now reserved and not yet in backlog.

Read from the sources Read from the source by an agent; quote matched mechanically against the fetched page; not yet reviewed by a person, 2026-09-24. Each value links the page it came from and quotes the sentence that carries it.