Lead time · US · weeks

Switchgear average lead time (Wood Mackenzie survey)

Switchgear average lead time (Wood Mackenzie survey), weeks, Q2 2025 to Q2 2025. Every value is listed in the table below.
PeriodValueSource
Q2 2025SourcedWood Mackenzie (Mind the gap, opinion) · 2025-10-15Open the source → weeksWood Mackenzie (Mind the gap, opinion) ↗ secondary reportPower transformer lead times also eased in Q2, falling by 10 weeks to an average of 128 weeks, while switchgear edged down to an average of 44 weeks.