Lead time · US · years

Typical/median time from interconnection request to commercial operation (projects built that year)

How this is computedThe latest value in a series minus the value before it, divided by the earlier value, same series and unit.5 (2022) → 5 (2023).Method →Code → vs 2022 · flat
Typical/median time from interconnection request to commercial operation (projects built that year), years, 2022 to 2023. Every value is listed in the table below.
Typical/median time from interconnection request to commercial operation (projects built that year), years, 2022 to 2023. Every value is listed in the table below.
PeriodTypical/median time from interconnection request to commercial operation (projects built that year) (years)
20225
20235
PeriodValueSource
2023SourcedLawrence Berkeley National Laboratory (Queued Up, 2024 edition) · 2024-04Open the source → yearsLawrence Berkeley National Laboratory (Queued Up, 2024 edition) ↗ primaryThe typical project built in 2023 took nearly 5 years from the interconnection request to commercial operations1, compared to 3 years in 2015 and <2 years in 2008."nearly 5 years".
2022SourcedLawrence Berkeley National Laboratory (Queued Up, 2023 edition) · 2023-04-06Open the source → yearsLawrence Berkeley National Laboratory (Queued Up, 2023 edition) ↗ primaryThe typical project built in 2022 took 5 years from the interconnection request to commercial operations1, compared to 3 years in 2015 and <2 years in 2008.Stated in years; later editions state months.