The constraints on your plan: how hard they bind, how long they last.

Bottleneck board · Lead times · What changed · Science pipeline · Site data Late

01The bottleneck board

The constraints judged to bind hardest right now, and which of them an event this month moved.

  1. EUV lithography scanners
    How this is computedSum of four judged scores, each 0–3: concentration + substitution + lead time + inelasticity.Method →Code →

    The machines that print the finest circuit patterns. One company on earth builds them.

    Verified
  2. EUV projection optics
    How this is computedSum of four judged scores, each 0–3: concentration + substitution + lead time + inelasticity.Method →Code →

    The mirrors inside those machines, polished flatter than anything else made. One supplier has ever achieved it.

    Verified
  3. Advanced packaging capacity
    How this is computedSum of four judged scores, each 0–3: concentration + substitution + lead time + inelasticity.Method →Code →

    Assembling several chips into one AI accelerator. How many exist is set here, not at the wafer.

    Verified
  4. Leading-edge foundry capacity
    How this is computedSum of four judged scores, each 0–3: concentration + substitution + lead time + inelasticity.Method →Code →

    Factories that can make chips at the newest generation. A handful exist, and the leader spends tens of billions of dollars a year adding more.

    Verified
  5. Grain-oriented electrical steel (GOES)
    How this is computedSum of four judged scores, each 0–3: concentration + substitution + lead time + inelasticity.Method →Code →

    The specially grown steel inside a large power transformer. Few mills can make it, and a new mill takes years.

    Verified
  6. High-voltage cable and switchgear
    How this is computedSum of four judged scores, each 0–3: concentration + substitution + lead time + inelasticity.Method →Code →

    The cables and switches that move power at high voltage. Cable order books run far ahead of output, and switchgear waits are long.

    Verified
  7. Large power transformer slots
    How this is computedSum of four judged scores, each 0–3: concentration + substitution + lead time + inelasticity.Method →Code →

    The big transformers a data centre needs to take grid power. Ordering one now means waiting more than two years.

    Verified
  8. Crucible-grade high-purity quartz sand
    How this is computedSum of four judged scores, each 0–3: concentration + substitution + lead time + inelasticity.Method →Code →

    An unusually pure sand used to line the crucibles that grow silicon crystals. Most of it comes from one place on earth.

    6 of 7 verified

Now · ranked by severity · judged 2026-09-15

Every bottleneck, filterable by technology and stage →

02Lead times, backlogs and queues

How long an order waits: the dated, sourced numbers behind each ‘years-long’ claim.

  • Gas Power equipment backlog + slot reservation agreementsBacklog · company: GE Vernova · Heavy-duty gas turbine order books
    SourcedGE Vernova (Q2 2026 earnings release, SEC 8-K Ex.99)Open the source → GW · 30 Jun 2026How this is computedThe latest value in a series minus the value before it, divided by the earlier value, same series and unit.100 (31 Mar 2026) → 116 (30 Jun 2026).Method →Code → vs 31 Mar 2026 · tightens
  • Prysmian Transmission backlogBacklog · company: Prysmian · High-voltage cable and switchgear
    SourcedPrysmian (Q2/H1 2026 results press release)Open the source → EUR bn · 30 Jun 2026How this is computedThe latest value in a series minus the value before it, divided by the earlier value, same series and unit.17 (31 Mar 2026) → 17 (30 Jun 2026).Method →Code → vs 31 Mar 2026 · flat
  • SourcedLawrence Berkeley National Laboratory (Queued Up, 2026 edition)Open the source → months · 2025How this is computedThe latest value in a series minus the value before it, divided by the earlier value, same series and unit.55 (2024) → 61 (2025).Method →Code → vs 2024 · tightens
  • Power transformer average lead time (Wood Mackenzie survey)Lead time · US · Large power transformer slots
    SourcedWood Mackenzie (Mind the gap, opinion)Open the source → weeks · Q2 2025How this is computedThe latest value in a series minus the value before it, divided by the earlier value, same series and unit.120 (2024) → 128 (Q2 2025).Method →Code → vs 2024 · tightens
  • Gas Services order backlogBacklog · company: Siemens Energy (Gas Services) · Heavy-duty gas turbine order books
    SourcedSiemens Energy (Earnings Release Q3 FY2026)Open the source → EUR bn · 30 Jun 2026How this is computedThe latest value in a series minus the value before it, divided by the earlier value, same series and unit.66 (31 Mar 2026) → 73 (30 Jun 2026).Method →Code → vs 31 Mar 2026 · tightens
  • Gas Power equipment backlog (firm orders)Backlog · company: GE Vernova · Heavy-duty gas turbine order books
    SourcedGE Vernova (Q2 2026 earnings release, SEC 8-K Ex.99)Open the source → GW · 30 Jun 2026How this is computedThe latest value in a series minus the value before it, divided by the earlier value, same series and unit.44 (31 Mar 2026) → 53 (30 Jun 2026).Method →Code → vs 31 Mar 2026 · tightens
  • Gas turbine slot reservation agreements (not in backlog)Backlog · company: GE Vernova · Heavy-duty gas turbine order books
    SourcedGE Vernova (Q2 2026 earnings release, SEC 8-K Ex.99)Open the source → GW · 30 Jun 2026How this is computedThe latest value in a series minus the value before it, divided by the earlier value, same series and unit.56 (31 Mar 2026) → 63 (30 Jun 2026).Method →Code → vs 31 Mar 2026 · tightens
  • Siemens Energy Grid Technologies order backlogBacklog · company: Siemens Energy (Grid Technologies) · High-voltage cable and switchgear
    SourcedSiemens Energy (Earnings Release Q3 FY2026)Open the source → EUR bn · 30 Jun 2026How this is computedThe latest value in a series minus the value before it, divided by the earlier value, same series and unit.49 (31 Mar 2026) → 51 (30 Jun 2026).Method →Code → vs 31 Mar 2026 · tightens

Every series, with charts and CSV →

03What changed

Capacity, outages, rules and milestones on the bottlenecks, newest first, each with its source.

  1. 2026-09-21
    NeutralPolicyKZ RU

    Kazatomprom on Russia's revised approval procedure for sulphuric acid exports (Resolution 1158)

    Uranium conversion and enrichment

    sightlineu3o8.com ↗secondary source

    The sentence that says so

    “Based on the information currently available, these measures do not prohibit sulphuric acid exports. Rather, they introduce a revised approval procedure for export volumes, which is expected to remain in effect until 31 December 2026.”

  2. 2026-09-14
    TightensPolicyEU

    The EU updates its dual-use control list to add atomic layer deposition equipment for molybdenum and ruthenium.

    Ruthenium, sputtering and ALD grade

    policy.trade.ec.europa.eu ↗official source

    The sentence that says so

    “Specifically, this update of the EU control list provides for the addition of new dual-use items, including: Semiconductor manufacturing and testing equipment and materials (e.g. Atomic Layer Deposition equipment for molybdenum and Ruthenium, equipment for the development and the inspection of Extreme Ultra-Violet masks and reticles, and single wafer cleaning equipment)”

  3. 2026-09-14
    NeutralCapacityCN

    ArcelorMittal and China Oriental open a 1.8 Mt/yr electrical steel joint venture in Changzhou; the first phase is non-oriented.

    Grain-oriented electrical steel (GOES)

    gmk.center ↗secondary source

    The sentence that says so

    “The total production capacity of the facility in Changzhou will be 1.8 million tonnes of high-quality electrical steel sheets.”

  4. 2026-09-13
    LoosensMilestoneCN MY

    Shanghai Electric wins its first overseas heavy-duty gas turbine order, 500 MW in Malaysia.

    Heavy-duty gas turbine order books

    prnewswire.com ↗official source

    The sentence that says so

    “Shanghai Electric Secures First Overseas Heavy-Duty Gas Turbine Order for 500 MW Malaysian Project / Shanghai Electric (SEHK: 02727, SSE: 601727) has achieved a milestone in the high-end overseas energy sector by securing the contract for Unit 3 of the Sarawak Samalaju Combined Cycle Gas Turbine (CCGT) project in Malaysia.”

  5. 2026-09-10
    TightensPolicyCN

    China’s November export controls will test whether rare-earth refining and recycling outside it can scale.

    Dysprosium metalDidymium (Nd-Pr) metal, magnet feedRare-earth magnet sintering

    fastmarkets.com ↗secondary source

    The sentence that says so

    “For decades, China has been the dominant supplier of the rare earths required to produce sintered neodymium-iron-boron (NdFeB) magnets: neodymium-praseodymium (NdPr), dysprosium and terbium.”

Every event →

04What could relieve them

Papers, preprints and grants collected this week against each bottleneck — unreviewed, sorted by stage on the pipeline.

Science feeds read 51m ago · Fresh

The science pipeline, by stage →